New UK AI datacentre could cause five times emissions of Birmingham airport | Greenhouse gas emissions

Wide new data can feed the increasing demand for Britain on artificial intelligence, more than five international airports.

Elsham Datacentre in Lincolnshire is on its way to a cost of 10 billion pounds, and it is expected that computer warehouses that thirst for 15 times the carbon dioxide will be released five times Birmingham airportIncluding taking off and landing.

A Planning application For the facility, which was presented nine miles east of Scunthorpe last month, a general consultation was closed within three weeks.

The documents estimate that the central data will consume 3.7 billion hours of energy, with the annual Co2 Emissions of 857,254 tons when running in full mile. This is based on the current mix of energy sources that operate on the national network.

The data center will also create a lot of excess heat suggested from glass with the ability to produce more than 10 tons of tomatoes per day.

Global technology companies are struggling to achieve carbon reduction. By 2030, the emissions of carbon dioxide from AI Datacentres will be six times the level of 2023, according to research By öko-institut in Germany. Greenpeace called for adding a diverse renewable energy capacity to national networks at the same time that a new centralization was created.

Microsoft recently recognized Five years after its commitment to become zero of carbon by 2030, its total emissions increased by 23 % due to factors, including artificial intelligence expansion. A 20 -year -old dead deal this week signed with a Nuclear power plant In Illinois, while Amazon and Google also invest in nuclear energy to feed the race for artificial intelligence dominance.

The data center is needed to train artificial intelligence models and operate artificial intelligence inspections, which are now routinely presented on billions of people by Google and Meta that require computing energy more than four to five times, According to estimates.

Climate experts believe that artificial intelligence can help fight global heating by making energy networks work more efficiently or accelerate the development of new carbon technologies.

Martha Dark, joint director of Foxglove, a non -profit organization in London, a campaign for a “more just technical future”, said the ELSham Planning app set two main mission of the UK government in a collision course.

She said: “The Prime Minister talked about the data centers that operate the artificial intelligence of technology, as magic beans miraculously met in the British economy in life, but he also promised in the elections to remove toxic pollution from Jonah and provide zero zero by 2050.” “It is time for the decision: Does the government want a better economic plan for Britain, or a better plan for Amazon, Google and Mita?”

State Documentation: “Elsham Tech Park Ltd will seek to buy green energy for the elbow, wherever possible.” Supporters believe in the form2 Emissions can be less than 850,000 tons annually if the national network becomes more green while the data center is operated in 2029.

The developer has excluded renewable energy sources on the site. If the system is working on biomass energy, the daily delivery of 100 large trucks of wood chips will require. Wind energy requires 10,000 turbines for wind with an area of ​​10,000 meters, while a five times the size of the GlastonBury Festival site is needed if it is driven by photovoltaic panels.

Putting the promotion of the previous newsletter

A clarification shows the size of the proposed Elsham Tech Park Park. Photo: Elsham Tech Park

A government spokesman said that “in a state of alert to the requirements of the authority that will lead to the development of artificial intelligence” and will use “responsible and sustainable sources”, with advanced standard reactors, which create a nuclear power, which plays a “particularly important role.”

“We are raising planning rules to facilitate the construction of nuclear power plants throughout the country,” said a spokesman.

Peter Kyle, Minister of Foreign Affairs of Science and Technology, described Datacenters as “artificial intelligence engines”, said the government It is targeted “Fast Building” to enhance the UK’s ability to build and operate artificial intelligence models.

Last month, Deputy Prime Minister, Angela Rainer, canceled a local council that rejected a plan to obtain data of one billion pounds in Abbots Langley at Herfordshire, Quoting from “The clear need and pressure to a new central capacity.”

Robert and Atham, the leader of the North Lincolnchy “It should be aware of resource management, but we must also have significant investments in the United Kingdom, artificial intelligence contributes to health and support the most vulnerable people. This is not only about searching in Google – Amnesty International is working to improve medical sciences and productivity,” said the council, which covers Elsham, said:

He pointed to an example of how the council has published the science of artificial intelligence to help the elderly stay at the top of their medicines, which allows them to stay at home for a longer period instead of moving to residential care.

The project will create 900 jobs. They said: “The region is an ideal location for the artificial intelligence data center due to the large investment that has been in the development of the most advanced clean energy group in the United Kingdom.” “It can reach a third of the winds of wind in the UK in the UK as well as reach 66 % of licensed carbon capture and storage in the UK.”